Refugee aid in Musterhausen
Checklist
Ser. No. Thema One-time  Recurring Settled
1 Organisational chart created x    
2 Roles defined and described x    
3 Goals identified x    
4 Goals clustered (goal tree created) x    
5 Environment analysed x    
6 Stakeholders identified   x  
7 Stakeholder portfolio created   x  
8 Stakeholder action plan created   x  
9 Phase plan drawn up x    
10 Sub-tasks and work packages identified and described x    
11 Work breakdown structure created and structured x    
12 Task list created and tasks personalised and prioritised   x  
13 Resources planned x    
14 Risks identified and listed   x  
15 Risk portfolio created   x  
16 Measures to reduce the risk value planned   x  
17 Status values (of the process flow) identified and reconciled x    
18 Controlling template (bar chart) created as pivot chart x    
19 Communication plan created and introduced x    
20 Meeting system set up x    
21 Status value list maintained on a regular basis   x  
22 Reporting system set up x    
23 Lessons learned implemented x    
24 Continuous improvement process implemented   x  
25 Final project report prepared x