Refugee aid in Musterhausen
Work breakdown structure
 (phase-oriented structure)
F-1
Structured integration of refugees in Musterhausen
RE
                                   
             
SM F-1.1
Project Management
F-1.2
Initialization phase
F-1.3
Planning phase
Konsolidierungsphase F-1.4
Implementation phase
F-1.5
Socio-cultural phase
F-1.6
 Final phase
             
SM F-1.1.1
Project organization
F-1.2.1
First-time Admission Facility
F-1.3.1
Resources
  F-1.4.1
Arrival
F-1.5.1
Work
F-1.6.1
Completion of the asylum procedure
WP F-1.1.1.1 Kick-Off Event F-1.2.1.1 Registration F-1.3.1.1 Helper organisation   F-1.4.1.1 Welcome F-1.5.1.1 Vocational care F-1.6.1.1 Complete integration
WP F-1.1.1.2 Roles F-1.2.1.2 Allocation F-1.3.1.2 Resource allocation   F-1.4.1.2 Familiarisation with flat F-1.5.1.2 Education support  
F-1.1.1.3 Organisational chart F-1.2.1.3 Movement EA to KV F-1.3.1.3 Budget calculation       F-1.5.1.3 Minijobs  
WP F-1.1.1.4 Environment analysis F-1.2.1.4 Foreigners' Registration Office       F-1.5.1.4 Environmental projects  
SM F-1.1.2
Target planning
F-1.2.2
Document creation
F-1.3.2
Residential
  F-1.4.2
Initial equipment
F-1.5.2
Meeting place
F-1.6.2
Return perspective
WP F-1.1.2.1 Target definition F-1.2.2.1 Residenc toleration F-1.3.2.1 Accommodation search   F-1.4.2.1 Food F-1.5.2.1 Citizens' café F-1.6.2.1 PM qualification
WP F-1.1.2.2 Target tree F-1.2.2.2 Residence permit F-1.3.2.2 Provision   F-1.4.2.2 Clothes F-1.5.2.2 Working group meeting  
WP F-1.1.2.3 Requirement management F-1.2.2.3 Health insurance certificate F-1.3.2.2 Renovation   F-1.4.2.3 Toys F-1.5.2.3 Childcare  
SM F-1.1.3
Phase planning
F-1.2.3
Asylum Seekers' Benefits Act
F-1.3.3
Household contents
  F-1.4.3
Medical care
F-1.5.3
Club life
F-1.6.3
Rejection of the asylum application
WP F-1.1.3.1 Creative Techniques F-1.2.3.1 Organise disbursements F-1.3.3.1 Procurement   F-1.4.3.1 Procurement Sickness certificate F-1.5.3.1 Admission to local societies F-1.6.3.1 Deportation
WP F-1.1.3.1 Phase plan F-1.2.3.2 Distribute information F-1.3.3.2 Appeals for donations F-1.4.3.2 Accompaniment to the doctor F-1.5.3.2 Organ. Games afternoons  
    F-1.3.3.3 Stockpiling      
WP            
SM F-1.1.4
Time schedule and process planning
  F-1.3.4
Transfer
F-1.4.4
Interview
 
WP F-1.1.4.1 Work breakdown structure F-1.3.4.1 Data transmission ADD / KV F-1.4.4.1 Appointment in KV
WP F-1.1.4.2 Subtasks F-1.3.4.2 Allocation in municipality F-1.4.4.2 Appointment at BAMF
WP F-1.1.4.3 Work Package Descr. F-1.3.4.3 Transfer by bus or taxi F-1.4.4.3 Appointment in Job Centre
WP F-1.1.4.4 Task list    
WP F-1.1.4.5 Status value list    
SM F-1.1.5
Communication
  F-1.4.5
Education
WP F-1.1.5.1 Stakeholder-Management F-1.4.5.1 Registration Kita's
F-1.1.5.2 Communication matrix F-1.4.5.2 School registration
WP F-1.1.5.3 Meeting management F-1.4.5.3 Language courses
WP F-1.1.5.4 Protocol  
WP F-1.1.5.5 Reporting  
SM F-1.1.6
Risk Management
F-1.4.6
Work
WP F-1.1.6.1 Risk list F-1.4.6.1 Entry-level qualification
WP F-1.1.6.2 Risk portfolio F-1.4.6.2 Professional internships
WP   F-1.4.6.3 Selection of skilled workers
SM F-1.1.7
Resource planning
F-1.4.6.4 Education and training
WP F-1.1.7.1 Resource Gantt Line
WP F-1.1.7.2 Target/ actual analysis
Legend
Root element RE
Subtask Municipality SM
Subtask Municipality SM Subtask association municipality
Work package WP Work package
Work package WP Work package
Work package WP Work package